THE council has withdrawn its petition against HS2 Crewe to Manchester Bill after receiving reassurance its concerns had been addressed.
Cheshire East Council had been due to present its petitions to the HS2 select committee on Monday (March 13).
The Bill seeks the powers to construct and operate Phase 2b of HS2 and had its second reading in the House of Commons in June last year.
But after months of negotiations, the council received a package of commitments from both HS2 and the Government around the scheme’s impacts on the environment, landscape, ecology and local transport network.
The commitments received by the council from HS2 are known as ‘assurances and undertakings’ and include:
● Additional highway junction improvements;
● Road safety mitigations;
● Active travel improvements;
● The installation of adaptive signal technology to improve bus service efficiency on key construction routes;
● Assurances relating to environmental, ecology and biodiversity mitigation;
● Assurances relating to the impacts of construction traffic during key events held at Tatton Park.
Councillor Craig Browne, deputy leader of the council and chair of its highways and transport committee, said: "The council has been clear, whilst it is minded to support the HS2 scheme in principle and recognises the major economic benefits and opportunities it would bring, it also recognises there will be communities adversely affected by it and this support remains conditional.
"I am pleased through extensive negotiations, we have now secured a number of commitments from both HS2 Ltd and the Government – including in relation to the scheme’s impacts on the environment, landscape, ecology and local transport network – that collectively will provide a better outcome for Cheshire East and its communities.
"However, we are naturally very disappointed by the announcement from Government last week that construction of the HS2 route from Birmingham to Crewe is now delayed by two years.
"This means a delay in HS2 coming to Crewe, and a delay in the benefits and opportunities it would bring to the north being realised.
"Despite this, the Bill still remains in Parliament – irrespective of this announcement – and the petitioning process is an important opportunity for the council to formally raise its concerns and influence the phase 2b proposals before the Bill becomes an Act of Parliament.
"We needed to ensure we responded robustly to the proposals and that when the scheme is delivered, it is delivered in a way that provides the appropriate levels of mitigation and maximises the opportunities available, and that these are brought forward as early as possible."
Councillor Sam Corcoran, council leader, said: “I am pleased we can announce the package of assurances and undertakings we have received, and we have secured some significant opportunities and benefits through this process.
“I would like to make it clear withdrawing our petitions does not mean we have concluded our efforts to secure the council’s shared vision for an enhanced Crewe hub station that can accommodate between five to seven HS2 trains per hour, nor to seek the appropriate mitigation against the negative impacts of the scheme and its construction.
"The council will have further opportunity to influence the scheme and to petition the Bill as it progresses through Parliament and will continue to do this in consultation with local ward members and town councils."
The council has also secured a 'critical' commitment directly from the Government to fund and extensive appraisal on what work is required at Crewe Station to support HS2.
Comments: Our rules
We want our comments to be a lively and valuable part of our community - a place where readers can debate and engage with the most important local issues. The ability to comment on our stories is a privilege, not a right, however, and that privilege may be withdrawn if it is abused or misused.
Please report any comments that break our rules.
Read the rules hereLast Updated:
Report this comment Cancel